Program Timeline

A program timeline showing the phases that the program will progress through from October 2019 through September 2022. The program kicked-off in October 2019 and stakeholder engagement and communications will run throughout the entire project—that is, until September 2022. Between November 2019 and August 2020, documentation of what the RM3P is and how it will be implemented will occur. Project evaluation will run from April 2020 to September 2022. Solution team selection will occur between September and December 2020. System development and integration will occur between December 2020 and May 2022. Testing and implementation delivery will occur between June 2021 and September 2022.